The time frame for MDSAP (Medical Device Single Audit Program) registration for medical devices in the United States can vary depending on several factors, including the manufacturer’s readiness, the complexity of the audit, and the availability of the auditing organization. However, the general timeline for MDSAP registration typically follows these stages:
1. Preparation Time (3 to 6 months)
- Before the actual MDSAP audit, manufacturers need to ensure their Quality Management System (QMS) is compliant with ISO 13485 and other relevant regulatory requirements for the U.S. (e.g., FDA 21 CFR Part 820). This preparation phase includes reviewing and updating documentation, training staff, and addressing any gaps in compliance.
- The time required for preparation depends on how close the manufacturer is to meeting MDSAP requirements. If the company already has a robust QMS, this stage may be shorter.
2. Audit Scheduling (1 to 3 months)
- Once the manufacturer is ready, they must select an accredited auditing organization to conduct the MDSAP audit. Auditing organizations will typically schedule audits within 1 to 3 months after receiving the manufacturer’s request, depending on their availability and the complexity of the audit.
- Manufacturers need to coordinate with the auditing organization to finalize dates and prepare for the audit.
3. On-Site Audit (3 to 5 days)
- The MDSAP audit itself typically takes 3 to 5 days, depending on the size of the company and the number of facilities or product lines involved. During the audit, the auditors will review the QMS, inspect processes, evaluate records, and assess compliance with the regulatory requirements of the participating countries (including the U.S. FDA).
- If nonconformities are found, the audit may take longer to address these issues.
4. Audit Report and Corrective Actions (2 to 3 months)
- After the audit, the auditing organization will prepare an audit report that highlights any nonconformities or areas for improvement. This process typically takes 2 to 3 months.
- If nonconformities are identified, the manufacturer must implement corrective actions. The time needed for corrective actions will depend on the complexity of the issues and the company’s responsiveness.
5. MDSAP Certification Issuance (1 to 2 months)
- Once the audit report is reviewed and corrective actions are verified, the auditing organization will issue the MDSAP certificate. This typically takes 1 to 2 months after the audit report is finalized.
- The certificate will confirm that the manufacturer complies with the regulatory requirements of the FDA and other participating countries.
Total Time Frame:
- In total, the entire MDSAP registration process, from preparation to certificate issuance, usually takes 6 to 12 months. However, this timeline can vary based on the company’s readiness, the complexity of the audit, and the speed at which corrective actions are implemented.
For companies with an established QMS and minimal corrective actions, the process can be completed more quickly. However, for manufacturers who need significant changes or improvements, the timeline may be longer. It is important to plan ahead and ensure that all required documentation and processes are in place to avoid delays.